Datasheet
Application Guide
Detail Drawings

|
|
 
Excel-Coat Green-Line
Application Guide
Multi-Purpose Waterproofing Membrane:
Between Slab Waterproofing / Below Grade Subterranean Wall Waterproofing /
Under Tile Applications and Pond Linings
Materials & Tools
MATERIALS
- Excel-Coat Green-Line VPolyester Reinforcing Fabric
- Protection Fabric or Board
TOOLS
- 4" Paint BrushRoller Frame Roller Sleeve (3/4-1 inch Nap Roller)Razor KnifeTrowel
- Patching Spreader
Substrate Preparation
CONCRETE
- Curing of concrete shall be by means of water cure or dissipating
compounds. Curing compounds shall be approved by an authorized
representative of Excellent Coatings, Inc.Concrete shall be cured a minimum of 14 days prior to the
installation of membrane unless approved by an authorized representative
of Excellent Coatings, Inc.Concrete finish shall be a power metal float followed by a light
steel trowel and fine hair broom finish, or equivalent. Concrete surfaces shall be free of excessive roughness, voids,
protrusions or exposed aggregate.Metal shall be bonderized (etched and galvanized), rust-free and a
minimum 26 gauge.All tooled joints, control joints and moving structural cracks shall
be routed, primed and caulked with sealant approved by Excellent
Coatings, Inc.
- All holes, cracks, flashing junctures, joints, and other openings
should be detailed with a 10 mil. stripe coat embedded with GLT tape,
covered with an additional 10 mil. coat of Excel-Coat Green-Line V.
Application
HORIZONTAL
APPLICATION:
- Roll the Excel-Coat Green-Line V onto the deck surface all the rate
of 50 square feet per gallon. Immediately install (if used) the
reinforcing fabric into the wet coat. Smooth fabric with a trowel or
brush, making sure there are no wrinkles or bubbles in the fabric. Allow
to dry 4-6 hours. Dry times may vary.Note: The cured film thickness shall be 18-20 mils. with fabric and
12-15 mils. without fabric.Using care, visually inspect the membrane. Any wrinkles, blisters or
voids should be cut out and the waterproofing material reapplied.Allow approximately 8 hours to properly cure. Dry times may vary.Apply an additional coat of Excel-coat Green-Line V at an average
rate of 100 square feet per gallon.After installation of the second coat of Excel-Coat Green-Line V,
water test all horizontal surfaces. This should be done after the
membrane has cured at least 36 hours.If a Protection Fabric is used, roll a third coat of Excel-Coat
Green-Line V while still wet. Install the Protection Fabric in a smooth
and wrinkle free manner, lapping seams a minimum of 2". Allow
approximately 12 hours to cure. Dry times may vary.
- If Excel-Coat Green-Line V is used as an under- tile membrane,
install a slurry coat of Excel-Crete as a protection course over the
membrane instead of Protection Fabric, prior to installation of the
tile.
Note: The total cured film thickness of the complete waterproofing
system shall be 30-40 mils.
Under Tile Application over Plywood
Install metal lath and Excel Crete per the Excel Coat Fire System
application guide prior to installation of the Excel coat Green Line V
membrane and the Excel Crete slurry coat.
VERTICAL
APPLICATION:
- If concrete block is used instead of tilt-up concrete, the surface
to be waterproofed shall be smooth, and, if necessary, parging shall be
implemented prior to installing the waterproofing membrane.For additional strength, reinforcing fabric may be used.Apply a coat of Excel-Coat Green-Line V on the below-grade wall at
the rate of 50 square feet per gallon. Immediately install reinforcing
fabric (if used) into the wet coat. Smooth fabric with a trowel or
brush. Allow material to dry approximately 4-6 hours. Dry times may
vary.Roll a coat of Excel-Coat Green-Line V onto the vertical wall at a
rate of 100 square feet per gallon. Allow material to dry for
approximately 2-4 hours. Dry times may vary.Using care, visually inspect the membrane. Any wrinkles, blisters or
voids should be cut out and the waterproofing material reapplied.Roll a third coat of Excel-Coat Green-Line V at the rate of 100
square feet per gallon and install the Protection Fabric in a smooth and
wrinkle-free manner, lapping seams a minimum of 2". Allow total system
to cure approximately 12 hours before backfill begins. If drainage board
is to be used, consult your Excellent Coatings, Inc., representative for
product recommendations.Note: Colder weather will slow the curing process of all Excel-Coat
products.FYI: Excel-Coat Green-Line V is a copolymer that does not crack or
get brittle over time. This material can be brought up above the fill
line, to the stucco line or header; but it must be
painted/textured to protect membrane from damage.
10/01
|
|